Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


o Removal of existing curb and gutter, sidewalk, and driveways.


o   Installation of curb and gutter and sidewalk on the south side of Knight St., the west side of Crown Ln., and the west/south side Crown Dr.

o   Installation of asphalt patches along water main and water service trenches.

o   Grinding existing asphalt surface in preparation for asphalt surface paving.




·         Linneman Street

o Project substantially complete.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive


o    Grading existing parkways and installing topsoil.

o   Installation of asphalt patches along water service trenches.

o   Punch list work.

o   Installation of final surface course of asphalt.