Wednesday, August 5, 2015

KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water service installation began on Knight St. On Wednesday afternoon.

Thank you for all your patience and understanding as the water service work continues.

 

          Linneman Street

  •  Water main installation was completed on Linneman St. from Wedel Ln. to Meadowlark Ln.  
  • Fire hydrant and valve installation was also completed on Linneman St. between Wedel Ln. and Meadowlark Ln.
  • The water main was then tested and chlorinated.
  • Storm sewer removal and replacement also started this week and was completed on Wednesday.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water service installation will continue on Crown Ln. and Crown Dr.  During this process the contractor will knock on your door to notify of your water being shut down temporarily as they switch your service from the old water main to the new water main.                      Thank you for your patience as construction continues on your street.  

 

·         Linneman Street

  • A. Lamp is scheduled to begin final water main connections on Linneman St. at 7 locations on Linneman St. between Wedel Ln. and Meadowlark Ln.

 Thank you for all your patience and understanding as water main work continues.