Friday, July 10, 2015

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main and fire hydrant installation continued on Knight St.from Crown St. south to the dead end and on Crown Dr. from Knight St. to Crown St.

Thank you for all your patience and understanding as the water main installation continues.

 

          Linneman Street

  •  No work at this time.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water main on Knight St., Crown St. and Crown Dr. will be filled with water, pressure tested, chlorinated and water samples tested. 
  • Storm sewer and sanitary sewer will be repaired in various locations on Knight St., Crown St., and Crown Dr.

Crews may be in multiple locations in one day this week due to the smaller size of the storm and sanitary sewer repairs.  Thank you for your patience during this work.

 

·         Linneman Street

·       A. Lamp is scheduled to begin mobilization of equipment and traffic control.