Monday, July 27, 2015

KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main was chlorinated and tested on Knight St., Crown Ln. and Crown Dr.  During the process the fire hydrants were flushed and water samples taken.

Thank you for all your patience and understanding as the work continues.

 

          Linneman Street

  •  Water main installation began on Linneman St. from Wedel Ln. to Meadowlark Ln.  This work included installation by open cut trenching on the west portion of the project and directional drilling on the east portion of the project.
  • Fire hydrant and valve installation also began on Linneman St. between Wedel Ln. and Prairie Lawn Rd.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water service installation will begin on Knight St., Crown Ln., and Crown Dr.                        Thank you for your patience as construction continues on your street.

 

·         Linneman Street

  • A. Lamp is scheduled to complete water main and fire hydrant installation on Linneman St.
  • A. Lamp will begin testing and chlorinating the water main on Linneman St.

 Thank you for all your patience and understanding as water main work continues.