Monday, September 21, 2015


Knight/Crown

Work Completed Last Week:

·         No work completed last week as we wait for more favorable weather for sod.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.

·         Punch list work including clean up and minor repairs/adjustments to work completed.

 

Linneman

Work Completed Last Week:

·         Final punch list walk through with Public Works.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.

·         Punch list work including clean up and minor repairs/adjustments to work completed.

Friday, September 11, 2015


Knight/Crown

Work Completed Last Week:

·         Final leak detection testing of new water main.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.
·         Punch list work including clean up and minor repairs/adjustments to work completed.

 
Linneman

Work Completed Last Week:

·         Installation of traffic gate on Linneman St. between Rolling Pass and Prairie Lawn.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.
·         Punch list work including clean up and minor repairs/adjustments to work completed.

Friday, September 4, 2015


Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


o   Installation of remaining asphalt patches along water main and water service trenches.

o   Grading existing parkways in areas damaged by construction and installing topsoil.

o   Installation of final asphalt surface course.




·         Linneman Street

o Project substantially complete.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive

o   Punch list work including clean up and minor repairs/adjustments to work completed.

 

Please note that final landscaping will be completed when the weather appears more favorable for the growth and survival of sod.

 

·         Linneman Street

o   Punch list work including clean up and minor repairs/adjustments to work completed.

 
Please note that final landscaping will be completed when the weather appears more favorable for the growth and survival of sod.

Friday, August 28, 2015

Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


o Removal of existing curb and gutter, sidewalk, and driveways.


o   Installation of curb and gutter and sidewalk on the south side of Knight St., the west side of Crown Ln., and the west/south side Crown Dr.

o   Installation of asphalt patches along water main and water service trenches.

o   Grinding existing asphalt surface in preparation for asphalt surface paving.




·         Linneman Street

o Project substantially complete.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive


o    Grading existing parkways and installing topsoil.

o   Installation of asphalt patches along water service trenches.

o   Punch list work.

o   Installation of final surface course of asphalt.

Monday, August 24, 2015

Knight/Crown/Linneman
 


Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


Removal of existing curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.


o   Installation of curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.
 



·         Linneman Street
 
Installation of asphalt patching along water main trench.


o   Installation asphalt surface on Linneman St. from Wedel Ln. to Meadowlark Ln.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive


o    Removal of existing curb and gutter and sidewalk on the south side of Knight St., the west side of Crown Ln., and the west/south side Crown Dr.


o   Installation of curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.

o   Existing asphalt surface removal.
 
o   Installation of asphalt patching along water main and sewer trenches on Knight St., Crown Ln., and Crown Dr.


 
·         Linneman Street


o   Installation of traffic gate on Linneman St. between Prairie Lawn Rd. and Rolling Pass.
 

Monday, August 17, 2015


Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water service installation was completed on Knight St., Crown Dr. and Crown Ln. 
·  The final water main connection to the existing water system was completed late last week.

 
Thank you for all your patience and understanding during the underground utility work.

 
          Linneman Street

  • Existing asphalt pavement surface was milled off.
·  Removal and replacement of existing curb and gutter.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

·         Removal and replacement of curb and gutter.
 
 
 
·         Removal and replacement of damaged sidewalk.

 
·         Linneman Street

  • Pavement patching.
·     Pavement resurfacing.
 
 
 
·     Restoration and clean up.

 

 Thank you for all your patience and understanding as road work begins.

Monday, August 10, 2015


KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 
Knight Street, Crown Lane and Crown Drive
  • Water service installation continued on Crown Ln. And Crown Dr. on Monday and Tuesday.

Thank you for all your patience and understanding as the water service work continues.

 
Linneman Street
  •  Final water main connections were completed this week starting on Wednesday.

 

Work Anticipated This Week:

 
Knight Street, Crown Lane and Crown Drive
  • Water service installation will continue on Crown Ln. and Crown Dr.  During this process the contractor will knock on your door to notify of your water being shut down temporarily as they switch your service from the old water main to the new water main.                     
As work continues towards the dead end on Crown Ln. traffic may have to wait a few minutes for A. Lamp to clear the road.  Thank you for your patience as construction continues on your street.

 
Linneman Street
  • A. Lamp is scheduled to begin road work including curb and pavement patching.

 

 Thank you for all your patience and understanding as water main work continues.

Wednesday, August 5, 2015

KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water service installation began on Knight St. On Wednesday afternoon.

Thank you for all your patience and understanding as the water service work continues.

 

          Linneman Street

  •  Water main installation was completed on Linneman St. from Wedel Ln. to Meadowlark Ln.  
  • Fire hydrant and valve installation was also completed on Linneman St. between Wedel Ln. and Meadowlark Ln.
  • The water main was then tested and chlorinated.
  • Storm sewer removal and replacement also started this week and was completed on Wednesday.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water service installation will continue on Crown Ln. and Crown Dr.  During this process the contractor will knock on your door to notify of your water being shut down temporarily as they switch your service from the old water main to the new water main.                      Thank you for your patience as construction continues on your street.  

 

·         Linneman Street

  • A. Lamp is scheduled to begin final water main connections on Linneman St. at 7 locations on Linneman St. between Wedel Ln. and Meadowlark Ln.

 Thank you for all your patience and understanding as water main work continues.

Monday, July 27, 2015

KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main was chlorinated and tested on Knight St., Crown Ln. and Crown Dr.  During the process the fire hydrants were flushed and water samples taken.

Thank you for all your patience and understanding as the work continues.

 

          Linneman Street

  •  Water main installation began on Linneman St. from Wedel Ln. to Meadowlark Ln.  This work included installation by open cut trenching on the west portion of the project and directional drilling on the east portion of the project.
  • Fire hydrant and valve installation also began on Linneman St. between Wedel Ln. and Prairie Lawn Rd.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water service installation will begin on Knight St., Crown Ln., and Crown Dr.                        Thank you for your patience as construction continues on your street.

 

·         Linneman Street

  • A. Lamp is scheduled to complete water main and fire hydrant installation on Linneman St.
  • A. Lamp will begin testing and chlorinating the water main on Linneman St.

 Thank you for all your patience and understanding as water main work continues.

 

Monday, July 20, 2015

KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main and fire hydrant installation was completed On Knight St., Crown Ln. An Crown Dr.
  • Water main and fire hydrant installation was completed on Knight St., Crown Ln. An Crown Dr.
  • Water main was pressure tested and chlorinated.
  • Storm sewer and sanitary sewer spot repairs were completed On Knight St., Crown Ln. An Crown Dr.

Thank you for all your patience and understanding suing this work.

 

          Linneman Street

  •  No work at this time.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water main on Knight St., Crown Ln. and Crown Dr. will be sampled and tested. 

Work onsite may be slow this week while we wait for satisfactory water samples. Thank you for your patience this work.

 

·         Linneman Street

  • A. Lamp will begin water main and fire hydrant installation on Linneman St. by Wedel St. by open excavation.
  • A. Lamp will also have a subcontractor onsite installing water main on Linneman St. by directional drilling method.

 Thank you for all your patience and understanding during this work.

 

Friday, July 10, 2015

Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main and fire hydrant installation continued on Knight St.from Crown St. south to the dead end and on Crown Dr. from Knight St. to Crown St.

Thank you for all your patience and understanding as the water main installation continues.

 

          Linneman Street

  •  No work at this time.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

  •  Water main on Knight St., Crown St. and Crown Dr. will be filled with water, pressure tested, chlorinated and water samples tested. 
  • Storm sewer and sanitary sewer will be repaired in various locations on Knight St., Crown St., and Crown Dr.

Crews may be in multiple locations in one day this week due to the smaller size of the storm and sanitary sewer repairs.  Thank you for your patience during this work.

 

·         Linneman Street

·       A. Lamp is scheduled to begin mobilization of equipment and traffic control.

Monday, July 6, 2015

Water main construction continues.


Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water main installation continued on Knight St. from Pfingsten Rd. to Crown Dr. and on Crown St. from Knight St. south.

Thank you for all your patience and understanding as the water main installation continues.




          Linneman Street
  •  No work at this time.



Work Anticipated This Week:



·         Knight Street, Crown Lane and Crown Drive

  •  Water main installation on Crown St. from Knight St. to dead end and on Crown Dr. from Knight St. to Crown St.

  • Water main pressure test on portions of the water main on Knight St.



·         Linneman Street


o   No work anticipated.

Saturday, June 27, 2015

Water main installation begins.


Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive
  •  Mobilization of traffic control and equipment.

  • In-place grinding of the roadway in the location of the proposed water main trench.
 
  • Water main connection was made on the East side of Pfingsten Rd. at Knight St.

  • Water main installation on Knight St. from Pfingsten Rd. to Crown Dr.

Thank you for all your patience and understanding as the water main installation continues.




          Linneman Street
  •  No work at this time.



Work Anticipated This Week:



·         Knight Street, Crown Lane and Crown Drive
  •  Water main installation on Knight St. from Crown Dr. to the dead end located west of Crown Dr.
  • Water main installation on Crown St. from Knight St. to the south.



 

·         Linneman Street


o   No work anticipated.

Monday, June 22, 2015




Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive


  •       ·         Utility companies were onsite painting existing utility locations
  •       ·         Due to weather A. Lamp did not start work.


Work Anticipated This Week:



·         Knight Street, Crown Lane and Crown Drive


o     Mobilization of traffic control and equipment.


o   In-place grinding of roadway in the location of the proposed water main trench.


o   Water main connection late this week or early next week.




 

·         Linneman Street


o   No work anticipated.

Wednesday, June 17, 2015


Knight/Crown/Linneman

 

Work Completed Last Week:

      ·         Preconstruction meeting with A. Lamp Concrete Contractors, Inc.

·         Onsite coordination meeting and rough layout of water main with A. Lamp Concrete Contractors.

 

Work Anticipated This Week:

·         Knight Street, Crown Lane and Crown Drive

o     Mobilization of traffic control and equipment.

o   In-place grinding of roadway in the location of the proposed water main trench.

o   Water main connection late this week or early next week.

 

·         Linneman Street

o   No work anticipated.