Monday, September 21, 2015


Knight/Crown

Work Completed Last Week:

·         No work completed last week as we wait for more favorable weather for sod.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.

·         Punch list work including clean up and minor repairs/adjustments to work completed.

 

Linneman

Work Completed Last Week:

·         Final punch list walk through with Public Works.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.

·         Punch list work including clean up and minor repairs/adjustments to work completed.

Friday, September 11, 2015


Knight/Crown

Work Completed Last Week:

·         Final leak detection testing of new water main.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.
·         Punch list work including clean up and minor repairs/adjustments to work completed.

 
Linneman

Work Completed Last Week:

·         Installation of traffic gate on Linneman St. between Rolling Pass and Prairie Lawn.

Work Remaining:

·         Final landscaping to be completed when the weather appears more favorable for the growth and survival of sod.
·         Punch list work including clean up and minor repairs/adjustments to work completed.

Friday, September 4, 2015


Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


o   Installation of remaining asphalt patches along water main and water service trenches.

o   Grading existing parkways in areas damaged by construction and installing topsoil.

o   Installation of final asphalt surface course.




·         Linneman Street

o Project substantially complete.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive

o   Punch list work including clean up and minor repairs/adjustments to work completed.

 

Please note that final landscaping will be completed when the weather appears more favorable for the growth and survival of sod.

 

·         Linneman Street

o   Punch list work including clean up and minor repairs/adjustments to work completed.

 
Please note that final landscaping will be completed when the weather appears more favorable for the growth and survival of sod.

Friday, August 28, 2015

Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


o Removal of existing curb and gutter, sidewalk, and driveways.


o   Installation of curb and gutter and sidewalk on the south side of Knight St., the west side of Crown Ln., and the west/south side Crown Dr.

o   Installation of asphalt patches along water main and water service trenches.

o   Grinding existing asphalt surface in preparation for asphalt surface paving.




·         Linneman Street

o Project substantially complete.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive


o    Grading existing parkways and installing topsoil.

o   Installation of asphalt patches along water service trenches.

o   Punch list work.

o   Installation of final surface course of asphalt.

Monday, August 24, 2015

Knight/Crown/Linneman
 


Work Completed Last Week:


·         Knight Street, Crown Lane and Crown Drive


Removal of existing curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.


o   Installation of curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.
 



·         Linneman Street
 
Installation of asphalt patching along water main trench.


o   Installation asphalt surface on Linneman St. from Wedel Ln. to Meadowlark Ln.



Work Anticipated This Week:


·         Knight Street, Crown Lane and Crown Drive


o    Removal of existing curb and gutter and sidewalk on the south side of Knight St., the west side of Crown Ln., and the west/south side Crown Dr.


o   Installation of curb and gutter and sidewalk on the north side of Knight St., the east side of Crown Ln., and the east/north side Crown Dr.

o   Existing asphalt surface removal.
 
o   Installation of asphalt patching along water main and sewer trenches on Knight St., Crown Ln., and Crown Dr.


 
·         Linneman Street


o   Installation of traffic gate on Linneman St. between Prairie Lawn Rd. and Rolling Pass.
 

Monday, August 17, 2015


Work Completed Last Week:

 

·         Knight Street, Crown Lane and Crown Drive

  • Water service installation was completed on Knight St., Crown Dr. and Crown Ln. 
·  The final water main connection to the existing water system was completed late last week.

 
Thank you for all your patience and understanding during the underground utility work.

 
          Linneman Street

  • Existing asphalt pavement surface was milled off.
·  Removal and replacement of existing curb and gutter.

 

Work Anticipated This Week:

 

·         Knight Street, Crown Lane and Crown Drive

·         Removal and replacement of curb and gutter.
 
 
 
·         Removal and replacement of damaged sidewalk.

 
·         Linneman Street

  • Pavement patching.
·     Pavement resurfacing.
 
 
 
·     Restoration and clean up.

 

 Thank you for all your patience and understanding as road work begins.

Monday, August 10, 2015


KNIGHT/CROWN/LINNEMAN

Work Completed Last Week:

 
Knight Street, Crown Lane and Crown Drive
  • Water service installation continued on Crown Ln. And Crown Dr. on Monday and Tuesday.

Thank you for all your patience and understanding as the water service work continues.

 
Linneman Street
  •  Final water main connections were completed this week starting on Wednesday.

 

Work Anticipated This Week:

 
Knight Street, Crown Lane and Crown Drive
  • Water service installation will continue on Crown Ln. and Crown Dr.  During this process the contractor will knock on your door to notify of your water being shut down temporarily as they switch your service from the old water main to the new water main.                     
As work continues towards the dead end on Crown Ln. traffic may have to wait a few minutes for A. Lamp to clear the road.  Thank you for your patience as construction continues on your street.

 
Linneman Street
  • A. Lamp is scheduled to begin road work including curb and pavement patching.

 

 Thank you for all your patience and understanding as water main work continues.